ODISHA PROJECT

STATUS OF 2 X 660 MW THERMAL POWER PLANT AT DHENKANAL, ODISHA

BY CESC LIMITED


HIGHLIGHTS

 

  • Positioned as Pit-head Project (2x660 MW) in the District of Dhenkanal in Odisha.
  •  Investment made till date :  Rs. 75 Cr. approx.
  • Govt. of Odisha confirmed that the MoU fot this project is being extended shortly.
  • Super Critical Technology based units will be used in the Plant
  • Awaiting Coal linkage. This project is on the top of the priority list for grant of Coal Linkage

                                                                  

CLEARANCES AND APPROVALS             

               

LAND ACQUISITION :

 

# 90% of the land has already been acquired for this project. Balance land is Govt. Land which is in the process of transfer by the concerned Nodal Agency of Govt. of Odisha. 

 

WATER ALLOCATION :

 

# Required water has been allocated from the River Brahmani.

  

ENVIRONMENT CLEARANCE :

 

# First Stage Environment Clearance (ToR) issued by MoEF.

# EIA Study completed and Public Hearing done successfully.

# Final presentation will be made before MoEF for getting the EC as soon as sourcing of coal is finalized.

 

POWER PURCHASE AGREEMENT ( PPA ) :

PPA, Amended PPA and finally the revised PPA signed with GRIDCO, Odisha for State share of Power.

 

SOURCING OF COAL:

 # The only hurdle of this project is sourcing of coal. CEA had strongly recommended our application for coal linkage based on the progress of the project. Now it is pending with coal ministry.

# We will also participate in the future coal block auctioning

 