JHARKHAND ELECTRIC COMPANY LIMITED

 

STATUS OF 2x300 MW COAL BASED JHARKHAND
PROJECT

 

BACKGROUND

 

# Initially Project Site was identified at Amgachia Pokharia villages of Katikund Block of Dumka district near the allocated Mahuagarhi coal block to make it a pit head plant

 

# Water Clearance and 1st Stage environment vlearance (ToR) were obtained

 

# Applied for acquisition of land, notifications U/S of L.A. Act 1984 issued and requisite money was deposited with Govt. of Jharkahnd.  However, land acquisition could not be donedue to the stiff resistance offered by the  Concerned Villagers followed by associated Law and Order problems.

 

PRESENT STATUS 

 

ALTERNATE SITE IDENTIFIED IN THE VILLAGE DANRO OF SAME DISTRICT CLOSE TO THE COAL BLOCK.

 

PRESENT STATUS OF POWER PROJECT AT NEW SITE

 

LAND ACQUISITION :

 

Land Acquisition is in a very advanced stage after complying all the necessary formalities like conduction of Gram Sabha under PESA Act, issuance of Section 4.1 notification by Govt. etc 

 

Land is being acquired through "CONSENT AWARD METHOD" after getting the consent form from the villagers and consent was obtained for the major portion of Private land. Award for the same has been passed by the district administration after deposition of required money by us. 

      
Disbursement will be started after getting the consent of the rest of the private land. Alienation of Govt. land is also in an advanced stage 

 

WATER ALLOCATION

Required Water alloted from the river Bansloi and Agreement was signed 

 

ENVIRONMENT CLEARANCE

First Stage Environment Clearance (TOR) obtained.

 

EXTENSION OF MoU

Based on the progress of the project, Govt. of Jharkhand has extended the MOU which is valid upto Sept 2016 

 

COAL :  The main hurdle of the project is sourcing of fuel. Mahuagarhi Coal block was jointly allocated for this project with JAS infrastructure. The Coal was deallocated in Sept 2014 along with all the coal blocks allocated in the country followed by an order passed by the hon'ble Supreme Court 

 

We Are in the process of finding alternate source of fuel.

 